The US Foods Distribution Center was developed in several stages to ensure a seamless construction process:
Phase 1 – Design and Permitting (Q1–Q2 2021):
- Completion of conceptual design and schematic layouts.
- Environmental and traffic impact assessments.
- Permitting coordination for utility connections, including water, sewer, power, and stormwater management.
Phase 2 – Site Preparation (Q3–Q4 2021):
- Mobilization and site clearing of the designated parcel.
- Grading and soil stabilization, including geotechnical improvements to support a heavy-use logistics facility.
- Underground utility installation (water, sewer, electrical, storm drain).
- Foundation preparation and concrete slab-on-grade pour.
Phase 3 – Vertical Construction (Q1–Q3 2022):
- Erection of steel framing and structural supports for the warehouse and administrative offices.
- Exterior wall and roofing systems installed using high-insulation materials for thermal control.
- Integration of specialized warehouse components: refrigerated storage enclosures, perishable goods areas, and controlled humidity zones.
- Core and shell completion for the administrative office spaces.
Phase 4 – Equipment & Systems Installation (Q4 2022–Q1 2023):
- Installation of building systems: HVAC, electrical, fire suppression, and security infrastructure.
- Implementation of automated logistics and warehouse management systems.
- Fit-out of office interiors, employee facilities, and IT systems.
Phase 5 – Final Inspections, Commissioning & Opening (Q2 2023):
- Testing and commissioning of all mechanical, electrical, and life safety systems.
- Compliance inspections by Sacramento County Building Department, Cal/OSHA, and the Fire Marshal.
Phase 6 – Phase II CNG Fueling Facility (Q1 2025):
- Setup of CNG (Compressed Natural Gas) vehicle fueling infrastructure on-site, to support a sustainable fleet transition.